I'll bet Greg meant 360 MW...
>>8000 pulsers at 75 MW pulsed each.. 3 microsecond pulses
>> Each of the 1000 or so modulator stations needs to generate a
500kV, 2000A, 3uS pulse, at 120BPS.
That's a 1 GW pulse lasting 3 uS , or 3 kJoule/pulse, repeated at 120
pulses/second is 360 kW per modulator
1000 modulators is 360 MW...
Given that the "wall plug efficiency" is probably something around 60-70%,
you're looking at a cool 1/2 Gigawatt to run that baby..
But gosh, that's only 800-900 Amps per phase on the 275 kV line feeding in,
right?
Other high power sources that might be interesting..
Goldstone Deep Space Network has a 400 kW S band (2-3 GHz) transmitter
(continuous, not pulsed) for spacecraft commanding and radar
Arecibo has (or is upgrading to) a 1 MW transmitter (Probably continuous,
since they do planetary imaging)
There's a big radio station just south of the Texas border that has a 1MW+
transmitter (that's not EIRP folks.. that's the power to the feed network)
----- Original Message -----
From: "Tesla list" <tesla-at-pupman-dot-com>
To: <tesla-at-pupman-dot-com>
Sent: Sunday, December 15, 2002 12:34 PM
Subject: Re: IGBT's, pulsed power (was Re: Waveguide TC)
> Original poster: "Terry Fritz" <twftesla-at-qwest-dot-net>
>
> Hi,
>
> 360 MW will light a good sized city. A 360MW generating station would put
> a good spot and the map as would the coal strip mine to run it :o)) I
> "think" Greg meant like 360kW or maybe only 360W ;-))
>
> Cheers,
>
> Terry
>
>
>
> At 02:24 PM 12/15/2002 -0500, you wrote:
> >Keep in mind, most facilities using very high powered equipment like this
> >have additional generators on site
> >to convert loss energy (such as heat etc...) back into electricity which
> >they then sell back to the power company.
> >
> >Dan
> >
> >
> >
> >
> > > 360 MW is still a heap o' juice, though... at $0.10/kWh, it's going to
> >cost
> > > $36000 per hour.. Presumably they don't plan to run the thing when
spot
> > > rates are high...
> > >
> > > ----- Original Message -----
> > > From: "Tesla list" <tesla-at-pupman-dot-com>
> > > To: <tesla-at-pupman-dot-com>
> > > Sent: Sunday, December 15, 2002 9:06 AM
> > > Subject: Re: IGBT's, pulsed power (was Re: Waveguide TC)
> > >
> > >
> > > > Original poster: "Greg Leyh by way of Terry Fritz
<twftesla-at-qwest-dot-net>"
> > > <lod-at-pacbell-dot-net>
> > > >
> > > > Sorry, I didn't denote that the 75MW is the *peak* output
> > > > rating of the klystron.
> > > > The duty factor here is *extremely* low -- the total site
> > > > power should average less than 360MW.
> > > >
> > > >
> > > > >Original poster: "W.R. Langston <blangsto-at-iwvisp-dot-com>
> > > > >
> > > > >"8000 (or so) 75 MW..." plus significant losses I presume; so,
whose
> >what
> > > > >is powering this set up?
> > > > >>
> > > > >>
> > > > >>SLAC is engaged in the machine design of many subsystems
> > > > >>for the Next Linear Collider, including the pulsed power
> > > > >>modulators that will feed the 8000 or so 75MW x-band klystrons.
> > > >
> > > >
> > > >
> > > >
> > > >
> > >
> > >
> > >
> > >
> > >
>
>
>