Re: Biggg power & the Elecric company meet :{



Original poster: "robert & june heidlebaugh by way of Terry Fritz <teslalist-at-qwest-dot-net>" <rheidlebaugh-at-desertgate-dot-com>

David: a few years  passed , in Utah, I neaded 480V 400A 3 PHASE AND IT COST
Me $21,OO0 to go 50 ft with a meter. That did not include the electritian or
wire, only the power Co costs from the pole to the meter base with 3 pole
pigs.
    Robert    H
-- 


 > From: "Tesla list" <tesla-at-pupman-dot-com>
 > Date: Wed, 30 Jul 2003 08:04:05 -0600
 > To: tesla-at-pupman-dot-com
 > Subject: Re: Biggg power & the Elecric company meet :{
 > Resent-From: tesla-at-pupman-dot-com
 > Resent-Date: Wed, 30 Jul 2003 08:06:36 -0600
 >
 > Original poster: "by way of Terry Fritz <teslalist-at-qwest-dot-net>"
 > <Tesla729-at-cs-dot-com>
 >
 > In a message dated 7/29/03 9:18:04 PM Pacific Daylight Time,
 > tesla-at-pupman-dot-com writes:
 >> But be interesting if he had
 >> a rough guess as to the cost of such a thing.  I do know the cost of puling
 >> 400 amp 480 three phase in.  In this case can't tell the actual number in
 >> public, but lets just say it is staggering!!
 >
 >
 > Terry, Kevin, all,
 >
 > I was considering purchsing a piece of land and building a
 > house on it before I setled on the new house that I'm in now
 > that was already built and already HAD all of the utilities in-
 > stalled. Since the land was in a rural area of the county, I
 > was going to have to run nearly 1/2 mile of primary line to
 > the house site at a cost of $15 a FOOT! That would have
 > translated to well over $40K just to get power to the site!!
 > That was pretty much what made me decide that moving
 > to the 'burbs was good enough as opposed to moving to the
 > country :^))
 >
 > David Rieben
 >
 >